Buying a flat in a listed building in Madrid: what to check before renovating
· 6 min. read · by Christie's International Real Estate Madrid
A listed building in Madrid is one that appears in the catalogue of the city's General Urban Development Plan (Plan General de Ordenación Urbana), and its level of protection determines what works are allowed in each flat. It is worth checking before you buy, because it shapes the renovation project, the licence and the timetable for the works.
What is a listed building in Madrid?
Title 4 of the 1997 General Plan lists the buildings, premises and urban features that must be preserved. That list forms the Catalogue of Protected Elements, which includes a catalogue of buildings. According to the Protocol on heritage protection conditions published by Madrid City Council in 2011, a building's listing takes precedence over the rest of the planning rules, and the protection extends to the whole plot.
There is also protection by the Community of Madrid, for Sites of Cultural Interest (bienes de interés cultural, BIC), which is checked separately. A building may have municipal protection, regional protection, both or neither.

Protection levels for a listed building in Madrid
The General Plan distinguishes three levels. The table summarises what each one protects and the works mentioned in the 2011 Protocol.
| Level | What it protects | Works listed in the Protocol |
|---|---|---|
| Level 1, integral grade | The whole building, with mandatory restoration of its entire surface | Any intervention requires a planning licence |
| Level 2, structural grade | The structure as a whole and certain elements subject to mandatory restoration | Partial restructuring, partial refurbishment affecting protected elements, consolidation, restoration, exterior works and demolition |
| Level 2, volumetric grade | The building envelope | Restoration, exterior works and demolition |
| Level 3, partial grade | Only the elements marked on the building analysis plan | Works affecting those elements |
| Level 3, environmental grade | The façades, under the same regime as the partial grade | Same as the partial grade, except that the environmental grade allows replacement of the façade to be proposed |
The Protocol itself makes clear that a building listed at level 3 is not considered protected as such. The detail of the works allowed at each level is set out in Article 4.3.12 of the Planning Regulations (Normas Urbanísticas), which your architect should read before drawing up the project.
How to check a building's protection level
The City Council explains the procedure in its guide to the planning viewer (in Spanish). These are the steps:
- Open Madrid City Council's Visualizador Urbanístico (planning viewer). For municipal protection, it sends you to the Geoportal, which has the most up-to-date information.
- In the Geoportal, go to Mapas, Planeamiento vigente, Catálogo de Edificios.
- Find the building by street and number and click on it.
- Open the Protección Actual tab and read the Grado de Protección field.
- For protection by the Community of Madrid, check the BIC/BIP section under Mapas.
A single building may contain several commercial units. If the property includes one, open the detailed record and check that it corresponds to the unit you are interested in.
What the protection level means for the building permit
At the highest level, works are processed through a full planning licence (licencia urbanística). The Protocol describes two procedures: the standard ordinary procedure, which covers works such as restoration or demolition in level 1 and 2 buildings, and the shortened ordinary procedure for standard types of work. An accredited planning licence collaborating entity (ECU) can check feasibility and documentation before the application is submitted.
In most cases, Madrid City Council's Commission for the Protection of Historic, Artistic and Natural Heritage (CPPHAN) issues a mandatory but non-binding report. When the works affect a Site of Cultural Interest, a historic ensemble or an archaeological zone, the report is issued by the Community of Madrid's Local Historic Heritage Commission and is mandatory and decisive.
Where a work or use is generally restricted but might be feasible with a different approach, the Protocol provides for a special planning consultation with the CPPHAN, whose outcome is binding. It also warns that rebuilding is not a right, but something that must be expressly authorised.
The Protocol dates from 2011 and is based on the 1997 General Plan, so your architect should confirm that the procedure is still in force.

What to ask before buying a flat in a listed building
- Protection level and grade. Check them in the Geoportal as soon as you receive the proposal, before the viewing.
- Protected elements. At levels 2 and 3 they are marked on the building analysis plan. Ask which ones affect the specific flat.
- Community of Madrid protection. Check whether the building is listed as a Site of Cultural Interest, because that changes which body issues the report.
- Planned renovation. Describe it to an architect before making an offer. They will tell you whether it fits the building's level and which procedure applies.
- Previous licences. Ask the owner for the licences granted for previous works in the flat.
This article is for guidance only and is no substitute for advice from an architect or consultation with the City Council.
Buying to renovate in the right neighbourhood
Many of the early 20th-century buildings with high ceilings and mouldings are found in neighbourhoods such as Salamanca and Jerónimos. Our guide to buying to renovate explains what to check about the condition of the property, and buying a property in Madrid summarises the process. You can also read about the Salamanca district and the Jerónimos neighbourhood.
At Christie's International Real Estate Madrid we support buyers looking for a flat with character to renovate. You can browse our properties to renovate and, if you are considering a property in a listed building, our team will be happy to advise you via our contact page.
Frequently asked questions
How do I know if a building in Madrid is listed? You can check in Madrid City Council's Geoportal, under Mapas, Planeamiento vigente, Catálogo de Edificios. The Grado de Protección field appears in the Protección Actual tab.
What protection levels are there in Madrid? The General Plan distinguishes three: level 1, the highest, with an integral grade; level 2, with structural and volumetric grades; and level 3, with partial and environmental grades.
Can a flat in a listed building be renovated? Yes, with the appropriate licence and within what the building's level allows. At level 1, restoration of the entire surface is mandatory and any intervention requires a planning licence. An architect should confirm which works are possible.
Who reports on works in a listed building? In most cases, the City Council's CPPHAN issues a mandatory but non-binding report. If the works affect a Site of Cultural Interest, a historic ensemble or an archaeological zone, the Community of Madrid's Local Historic Heritage Commission issues a mandatory and decisive report.
Is a level 3 building protected? According to the City Council's 2011 Protocol, a building listed at level 3 is not considered protected as such. Only the specific elements marked on the building analysis plan are protected.